Basic Work Schedule 1 Week preparation of detail drawings, finalizing of quantities and ordering of materials. 1 – 2 Weeks preparation on and off site. 3 – 4 Weeks to glue EPS bars 25kg/m3, 40mm thk, width : 100mm on the between of the profiles of the existing steel deck to full filled the valley, […]